Commissioned by PNEM Netwerk B.V., transport division, intensive work was carried out last year on the 150 KV Helmond- Oost substation. A total of approximately 5000 m² of hot-dip galvanized construction was provided with a so-called duplex system.
In order to perform these activities in the vicinity of high voltage, numerous requirements must be met. Our employees at the PNEM must hold the following certificates:
- Safety certificate “RSA part 1”
- Certificate “working safely in high-voltage pylons”
- Certificate “Training fall protection in high-voltage pylons”
All our employees hold Certificate Safety 1 and sixteen employees hold Certificates 2 and 3.