IHC OFFSHORE & MARINE AWARDED CONTRACT TO VAN DER ENDE

[column]The 45-year-old tower crane 15 will be given a completely new paint system during the month of July. We have commissioned Wiko Isolatietechniek and Steigerbouw BV to provide safe access to the crane and to ensure proper shielding of the work so that no damage to the environment occurs.

[/column]

[column]The scaffolding structure is constructed so that in case of emergency, the crane can still be used for transport work with minimal modifications without having to dismantle the entire scaffolding structure. To achieve this, the scaffold structure was built from the pivot point at a height of 20 meters to the boom at a height of 54 meters. [/column]

[column]The lead time for this project has been minimized to 4.5 weeks due to a scheduled ship at the dock, during which we are required to perform all scaffolding and conservation work.[/column]