The railroad bridge in Zaltbommel

Van der Ende has thoroughly renovated the 1.2 km long railroad bridge near Zaltbommel, one of the oldest riveted bridges in the Netherlands. The tar-like flint coat was removed using 2,000 bar water pressure, after which 42,000 m² of steel was de-rusted and provided with a durable 3-layer coating system. Thanks to an efficient approach, the project was completed 1.5 years ahead of schedule.

Removing flintcoat

One of the longest (Length 1.2 km) and oldest riveted railroad bridges in the Netherlands. In the 1960s provided with a so-called flintcoat. A tar-like fairly hard coating sometimes up to a centimeter thick.

" " The assigned work was performed satisfactorily and in good cooperation and delivered on time."

A.C.P. Knobel (ProRail)

Application of 3-layer coating system

The underside consists of approximately 42,000 m2 of steel. Of this, approximately 12,000 m2 had flint coating. This coating was removed by high-pressure water 2,000 bar. After this, the 42,000 m2 of steel was further de-rusted and roughened and provided with a 3-layer coating system.

Save time

The project was completed 1½ years early.

Contact With Van der Ende

Curious about what we can do for you in the field of steel preservation?
If you have questions or need additional clarification, please fill out the form below and our specialists will respond promptly. For short questions, please call us at 010 – 472 11 88.
We will be happy to look at the possibilities for your business with you.

    My Industry:
    IndustryInfrastructureLogisticsMaritimeFoodOther

    Call me for an appointment